ACTC's Pine Grove Corridor Project - John Plasse's side of the story

In her Nov. 23 blog, writer Katherine Evatt wrote, "Do planning and public participation count? Maybe not in Amador County," taking on the issue of Amador County Transportation Commission member John Plasse calling for a reconsideration vote less than one month after the commission - including Plasse - voted unanimously to approve the Pine Grove Corridor ImprovementProject. The blog went viral on Facebook, and comments criticizing Plasse - including my own - reached the Amador County District 1 Supervisor. On Nov. 26, Plasse asked to speak with me personally to talk about my concerns. During our discussion, he elaborated on his response to Evatt, why he voted the way he did, and why he's asking for a reconsideration vote.


GB: What is your response to Katherine's blog?

JP: I would say that most of what Katherine put on her post - sans the offer to provide the  feathers to tar and feather me with from Mr. Matt Turner, -I believe was the name- aside from that, most of what Katherine put on her post is reasonably accurate. Frankly, Katherine suffers from the sins of omission to a certain extent in her post. If she's trying to put information out there, she did not put out that the vote was to spend an additional $5 million to $6 million to get the Pine Grove project "shovel ready," which would then, likely as a result of the community taking the stance that now that you've got $8 million invested in it, how can you possibly not build it? That would cost an additional $30 million or so to complete build-out. And then that money - what's called the STIP money - State Transportation Improvement Program - comes to Amador County in two-year cycles. To commit that expenditure to the Pine Grove Project would be encumbering all of Amador County's STIP monies, making none available for any other worthwhile projects in Amador County. It would encumber those through the year 2028. So the next 15 years, and other provisions that have been discussed in the background as far as partnering back in the tri-counties MOU with Alpine and Calaveras counties, could potentially extend that encumbrance or commitment of Amador STIP funds into the 2030 years. This is per ACTC staff's presentation to me personally.

GB: When you voted to approve everything in October, why are you changing your mind now?

JP: I voted with the majority in October because we had been in a very lengthy meeting. The Board was of no mind to have a full and complete discussion on this - that was pretty obvious. The only way I or anybody else can request a reconsideration of the vote is to be a member of the voting majority. Those are the provisions for a reconsideration vote. It keeps a member of the minority that lost on a vote from constantly calling for a reconsideration. So I voted with the majority so I could do just that.

I have spoken with Charles Field about this proposal, about the presentation that was given to me by Neil Peacock privately when I began wanting to place this as reconsideration vote. Neil took the time to give me about a two-hour personal explanation of the historical context of the Pine Grove Project and what documents support it and how they support it and why they support it. Again, it was about two hours and Charles Field has advised that if the commission votes to have a reconsideration vote, that we schedule that reconsideration vote for early next year, and plan to have an entire workshop specifically going into the funding timeline, the funding encumbrance timeline, as I just discussed out to 2028 going into the 2030s, which I find very interesting because if the commission needs a full workshop to fully understand the funding commitments that it's making to a singular project in Amador County, then why didn't we have the workshop before we made the initial vote? If it's necessary in a reconsideration, it's necessary in the initial vote. And I don't feel the commission was fully apprised of all the information out there.


If you are interested in providing your input, attend the ACTC meeting Nov. 27 at 9 a.m. at the ACTC office - 117 Valley View Dr. in Sutter Creek. Please see the agenda for more information.